ROAN EDGE
LANDFILL SITE
Stephenson Halliday produced
the Supporting Statement to accompany a planning application
and carried out discussions with the Planning Authority, which
resulted in an approval by Cumbria County Planning and Development
Committee for the landfill of inert waste and recycling operations
at Roan Edge Landfill Site, Killington. The Roan Edge site is
an integral part of the recycling and waste management operations
carried out in South Lakeland. At the same time as making the
application to extend the timescale the submitted Supporting
Statement amends the proposals to better accommodate the increase
in recycling operations which has occurred over recent years.
The engineering of void space to accommodate the recycling and
processing operations would provide additional landfill capacity
lengthening the life of the site.
Following consultation during the planning application, the County
Council had concerns about the visibility of the operations in
views from the west. To demonstrate that the visual impact would
not be significant a series of photomontages were produced to show
the phases of development over time. This was an important factor
in ensuring the success of the planning application.
Client: L&W
Wilson (Endmoor) Ltd.
|